المؤلف:
دار النشر: Project Gutenberg
الصفحة رقم: 4

exceedingly high.

In the case of the concreting, inability to purchase a hoist and motor and the high cost of renting the same, together with the delays mentioned, added greatly to the unit cost.

When it is considered that the cost of plastering covers that of four coats over the entire inside of the tank and three more over about one-third of it, it does not appear so high, especially in view of the high rate of wages paid.

The cost per yard for concrete alone was $25.126, and this is probably about 25% in excess of the cost of the same class of work executed under more favorable conditions as to location, weather conditions, etc.

TABLE 1.—Cost of High-Level Tower, Victoria Water-Works. (412 cu. yd.)

  Total Cost. Unit Cost.
Rate per hour. Amount. Complete. Labor. Material.
Preliminary Work:          
Labor, Carpenter $0.50 $11.00      
Labor 0.344 64.94      
   " 0.281 249.67 $325.61 $0.790  
Material   133.62 133.62   $0.324
Forms:          
Buildings, shifting and stripping:          
Labor, Carpenter 0.50 1,832.99      
Labor 0.344 80.85      
   " 0.281 563.84 2,477.68 6.014  
Material:          
Lumber   583.49      
Hardware   325.51      
Miscellaneous   13.90 922.90   2.240
Scaffold:          
Erecting and tearing down:          
Labor, Carpenter 0.50 693.00      
Labor 0.344 350.59      
   " 0.281 117.27 1,160.86 2.818  
Material:          
Lumber   487.77      
Hardware   202.79 690.56   1.676
Concreting:          
Labor 0.50 142.00      
   " 0.344 11.00      
   " 0.281 947.81 1,100.81 2.672  
Material:          
Rock   317.30      
Sand   385.72      
Cement   1,581.97      
Motor and Hoist:          
Rental   406.56      
Power   83.53 2,735.08  